titleDecember (12th December 2023)

Release date 12th December 2023

🐞 Bug fixes

  • The job was not scheduled for users with different time zones that were not present in the DB which caused no leave accrual for that user, now fixed.

  • The calendar Owner name was not displayed in linked format on Add existing calendar pop-up window, now fixed.

  • The confidence status and score don't get changed automatically to Not Applicable for Metric and To Do KR when status of objective is changed to Ready for Grading, fixed.

  • System was displaying blank page when a large file is added as an attachment to leave application, fixed.

  • Minor bug fixes.

Expand
titleDecember (01st December 2023)

Release date 01st December 2023

🎁 Enhancements

  • Introduced the possibility of creating default leave calendars

  • Easier calendar setup & filtering introduced that enhances the calendar creation and filtering

  • Revamped the Manage tab under Leaves for a better UX experience for users

🐞 Bug fixes

  • Team members could see their confidential review forms on their reviewer’s user profile’s forms tab, now fixed.

  • The disable option was not displayed for leave types associated with leave requests, fixed.

  • The system was taking time to add users midway in distribution when the number of users was more, fixed.

  • Other minor bug fixes.

Expand
titleNovember (09th November 2023)

Release date 09th November 2023

🐞 Bug fixes

  • On Browse OKR’s list view, the progress bar for Jira issues was not displayed. I was only displaying progress %, now fixed.

  • In Date and Time settings, blank date format are allowed, although date format is mandatory, now fixed.

  • Multiple duplicate history entries were getting inserted in database for leave policy and workweek scheme, fixed.

  • Unknown Error occurred while adding users in midway into the distribution, fixed.

  • Same objective alignment was getting added multiple times to an objective, now fixed.

  • No history was displayed for Leave policy, Holiday scheme, and workweek scheme on User’s history, now fixed.

  • Objective status was not getting updated to In progress even if TO DO KR is In progress, now fixed.

  • Some other minor bug fixes.

...